NHHIP Environmental
Impact Statement (EIS) Timeline
________________________________________________________________________
2011
•
Publish the Notice of Intent to prepare an Environmental Impact
Statement (EIS) – Federal Register, October 24, 2011; Texas Register,
October 14, 2011
•
Develop Draft Need and Purpose Statement and Draft Agency Coordination
and Public Involvement Plan
•
Request Public and Agency Input on Draft Need and Purpose Statement
and Draft Agency Coordination and Public Involvement Plan
•
1st Agency Scoping Meetings: November 14, 2011
•
1st Public Scoping Meeting: November 15 and 17, 2011
2012
•
Develop Range of Project Alternatives
•
Develop Alternative Evaluation Methodology to Assess
Impacts
•
Request Public and Agency Input on Range of Alternatives and Present
Approved Need and Purpose Statement and Agency
Coordination and Public Involvement Plan
•
2nd Agency Scoping Meetings: October 10, 2012
•
2nd Public Scoping Meeting: October 9 & 11, 2012
•
Analyze Range of Alternatives to Determine Preliminary
Alternatives to be Studied in Detail
2013
•
Request Public and Agency Input on Reasonable Alternatives
•
3rd Agency Meetings: November 13, 2013 and November 14, 2013
•
3rd Public Meeting: November 14 & 19, 2013
2014/2015
•
Refine Alternatives to One Proposed Recommended Alternative
2015
•
Request Public and Agency Input on Proposed Recommended Alternative
•
4th Agency Meetings: April 22, 2015
•
4th Public Meeting: April 23, 28, and 30, 2015
2017
•
Complete Draft Environmental Impact Statement (Draft EIS)
•
Request Public Input on Draft EIS and Circulate for Comment
•
Public Hearing (May 9 and 11, 2017)
•
Meeting (May 15, 2017)
2017/2018
•
Respond to Draft EIS Comments
•
Prepare Final Environmental Impact Statement (Final EIS)
2019
•
Prepare Final EIS
2020
•
Circulate Final EIS for Comment
•
Record of Decision
|